Polygon and the Contractor utilized a sheet metal ducting and stack system to deliver dehumidified air onto each floor of the Kaiser Permanente Hospital.
Polygon was able to save the building owner 194 KW in power consumption (roughly $22,410 per month). The system worked so well, that even though it had been slated to be used for seven months, the Contractor did not need it for the entire contract length.